Completed queue projects in New Jersey (2012 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown10188 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn223,823 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Eagle Point
Gas
63.0 MWOperating Gloucester, NJPJM Nov 20122015
Newark Energy Center
Gas
45.0 MWOperating Essex, NJPJM Jun 20122015
Lakewood Cogeneration Plant
Gas
20.0 MWOperating Ocean, NJPJM Oct 20122015
Ocean Peaking Power
Gas
20.0 MWOperating Ocean, NJPJM Oct 20122015
EF Kenilworth LLC
Gas
17.9 MWOperating Union, NJPJM Jan 20122015
Marina Thermal Facility
Gas
7.5 MWOperating Atlantic, NJPJM Dec 20122014
French's Landfill Solar Farm
Solar
5.0 MWOperating Ocean, NJPJM Aug 20122014
Deptford (Kinsley Solar)13kV
Solar
5.0 MWOperating Gloucester, NJPJM Oct 20122015
Warren County Landfill
Solar
3.8 MWOperating Warren, NJPJM Jun 20122014
Reeve's Station South
Solar
1.0 MWOperating Burlington, NJPJM Apr 20122013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)