United States β€Ί Grid β€Ί Interconnection queues β€Ί New Hampshire

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in New Hampshire (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown372.4 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn133.0 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
GRE Capacity Uprate
Gas
41.0 MWOperating Rockingham, NHISO-NE Nov 2014target 2017
Newington Gas Turbine Uprate
Gas
27.9 MWOperating Rockingham, NHISO-NE Dec 2014target 2015
Jericho Wind expansion
Onshore wind
3.5 MWOperating Coos, NHISO-NE Feb 2014target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)