United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Nevada (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3487 MW
Active in queue755 MW4 requests
Agreement signed755 MW4 requests
Withdrawn183,053 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Yellow Pine 2
Solar + storage
400 MWOperating Clark, NVCAISO May 2016target 2019
Geothermal project Company HD, Lander County
Geothermal
48.0 MWOperating Lander, NVWest Mar 2016target 2018
Geothermal project Company HE, Churchill County
Geothermal
38.5 MWOperating Churchill, NVWest Mar 2016target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)