Completed queue projects in Montana (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3305 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn9867 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 542, Carbon County
Onshore wind Β· PacifiCorp
240 MWOperating Carbon, MTWest Jan 2014target 2020
Gas project J405, Richland County
Gas
40.0 MWOperating Richland, MTMISO Nov 20142017
Onshore wind project 172, Sweet Grass County
Onshore wind
25.0 MWOperating Sweet Grass, MTWest Aug 20142015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)