Requests shown5769 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn5769 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2011-052, Jackson County
Gas
250 MWWithdrawn / abandoned Jackson, MOSPP Sep 2011target 2014
Gas project GEN-2011-053, Buchanan County
Gas
250 MWWithdrawn / abandoned Buchanan, MOSPP Sep 2011target 2014
Onshore wind project GI-44, Nodaway County
Onshore wind
100 MWWithdrawn / abandoned Nodaway, MOSoutheast Jan 2011target 2012
Onshore wind project GI-46, Sullivan County
Onshore wind
88.8 MWWithdrawn / abandoned Sullivan, MOSoutheast Mar 2011target 2013
Onshore wind project GI-45, Jasper County
Onshore wind
80.0 MWWithdrawn / abandoned Jasper, MOSoutheast Feb 2011target 2014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)