United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Missouri (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2705 MW
Active in queue4,791 MW20 requests
Agreement signed705 MW2 requests
Withdrawn234,881 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GI-121, Randolph County
Gas
460 MWAgreement signed Randolph, MOSoutheast May 2024target 2030
Solar project GI-120, Randolph County
Solar
245 MWAgreement signed Randolph, MOSoutheast Apr 2024target 2031

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)