πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Minnesota (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3212 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn182,685 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J183, Rock County
Onshore wind
200 MWOperating Rock, MNMISO Nov 2010target 2012
Other project J171, Swift County
Other
7.0 MWOperating Swift, MNMISO Oct 20102010
Onshore wind project J112, Winona County
Onshore wind
4.9 MWOperating Winona, MNMISO Jan 20102009

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)