United States β€Ί Grid β€Ί Interconnection queues β€Ί Maryland

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Maryland (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7186 MW
Active in queue451 MW5 requests
Agreement signed309 MW3 requests
Withdrawn48721 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Jones Farm Lane Solar
Solar
64.0 MWOperating Queen Anne's, MDPJM Apr 20162025
Richfield Solar and Storage
Solar
50.0 MWOperating Dorchester, MDPJM Apr 20162024
Pondtown Solar 2
Solar
20.0 MWOperating Queen Anne's, MDPJM Feb 20162022
Pondtown Solar 2
Solar
20.0 MWOperating Queen Anne's, MDPJM Apr 20162022
Calvert Cliffs Units 1 and 2 (f/k/a PJM Queue M04)
Nuclear
19.2 MWOperating Calvert, MDPJM Jun 20162023
Hagerstown Plant
Solar
10.0 MWOperating Washington, MDPJM Apr 20162020
Rollins Avenue Phoenix
Solar
2.5 MWOperating Prince George's, MDPJM Apr 20162019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)