Completed queue projects in Maryland (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5139 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn31442 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Perry Road Solar
Solar
118 MWOperating Somerset, MDPJM Oct 20142017
Frederick Road Solar
Solar
9.0 MWOperating Frederick, MDPJM Oct 20142017
Worcester North
Solar
5.0 MWOperating Worcester, MDPJM Apr 20142019
Pinesburg Solar Project
Solar
4.3 MWOperating Washington, MDPJM Oct 20142020
Worcester South
Solar
2.6 MWOperating Worcester, MDPJM Apr 20142019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)