Coal interconnection queue in Kentucky

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2348 MW
Active in queue348 MW2 requests
Agreement signed0.0 MW0 requests
Withdrawn73,611 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Coal project G003, Trimble County
Coal
174 MWIn study Trimble, KYMISO Dec 1998target 2004
Coal project G002, Trimble County
Coal
174 MWIn study Trimble, KYMISO Dec 1998target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)