United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Kentucky (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown51,459 MW
Active in queue27.0 MW2 requests
Agreement signed27.0 MW2 requests
Withdrawn51,459 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project LGE-GIS-2011-004, Mercer County
Gas
880 MWWithdrawn / abandoned Mercer, KYSoutheast May 2011target 2018
Gas project LGE-GIS-2011-001, Oldham County
Gas
450 MWWithdrawn / abandoned Oldham, KYSoutheast Jan 2011target 2015
Coal project X4-025, Greenup County
Coal
80.0 MWWithdrawn / abandoned Greenup, KYPJM Nov 2011target 2018
Gas project LGE-GIS-2011-002, Jefferson County
Gas
30.0 MWWithdrawn / abandoned Jefferson, KYSoutheast Feb 2011target 2015
Other project X2-090, Martin County
Other
19.0 MWWithdrawn / abandoned Martin, KYPJM Jul 2011target 2012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)