πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Iowa (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown61,074 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn164,962 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J411, Ida County
Onshore wind
300 MWOperating Ida, IAMISO Nov 20142014
Onshore wind project J412, Ida County
Onshore wind
200 MWOperating Ida, IAMISO Nov 20142019
Onshore wind project J416, Franklin County
Onshore wind
200 MWOperating Franklin, IAMISO Nov 20142017
Onshore wind project J344, Mahaska County
Onshore wind
169 MWOperating Mahaska, IAMISO May 20142017
Onshore wind project J343, Adams County
Onshore wind
150 MWOperating Adams, IAMISO May 20142016
Hydro project J329, Marion County
Hydro
55.0 MWOperating Marion, IAMISO Apr 20142019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)