Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4400 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn5869 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J285, O'brien County
Onshore wind
250 MWOperating O'brien, IAMISO May 20132017
Onshore wind project J274, Madison County
Onshore wind
100 MWOperating Madison, IAMISO Mar 20132014
Coal project J279, Woodbury County
Coal
30.0 MWOperating Woodbury, IAMISO Mar 20132016
Onshore wind project J289, Madison County
Onshore wind
20.0 MWOperating Madison, IAMISO Jul 20132013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)