Withdrawn queue requests in Indiana (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown51,959 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn51,959 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project Y3-063, Lake County
Gas
1,161 MWWithdrawn / abandoned Lake, INPJM Mar 2013target 2018
Onshore wind project J312, Clinton County
Onshore wind
201 MWWithdrawn / abandoned Clinton, INMISO Nov 2013target 2017
Onshore wind project J313, Montgomery County
Onshore wind
201 MWWithdrawn / abandoned Montgomery, INMISO Nov 2013target 2017
Onshore wind project J054, Tipton County
Onshore wind
198 MWWithdrawn / abandoned Tipton, INMISO Jan 2013target 2011
Onshore wind project J270, Newton County
Onshore wind
198 MWWithdrawn / abandoned Newton, INMISO Mar 2013target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)