πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Indiana (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5830 MW
Active in queue989 MW6 requests
Agreement signed350 MW2 requests
Withdrawn214,890 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J838, White County
Onshore wind
200 MWOperating White, INMISO Jun 20172021
Onshore wind project J837, White County
Onshore wind
200 MWOperating White, INMISO Jun 20172021
Solar project J913, White County
Solar
200 MWOperating White, INMISO Jun 20172022
Bitter Ridge Wind Farm
Onshore wind
130 MWOperating Jay, INPJM Mar 20172020
Riverstart Solar Park III
Solar
100 MWOperating Randolph, INPJM Mar 20172024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)