Completed queue projects in Indiana (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5370 MW
Active in queue245 MW2 requests
Agreement signed175 MW1 requests
Withdrawn133,931 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Riverstart Solar Park
Solar
100 MWOperating Randolph, INPJM Oct 20162021
Riverstart Solar Park
Solar
100 MWOperating Randolph, INPJM Oct 20162021
Solar project J759, Spencer County
Solar
70.0 MWOperating Spencer, INMISO Nov 20162020
Lawrenceburg Generating Plant
Gas
50.0 MWOperating Dearborn, INPJM Oct 20162019
Lawrenceburg Generating Plant
Gas
50.0 MWOperating Dearborn, INPJM Oct 20162019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)