United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Idaho (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown301,438 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn301,438 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

30 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Hydro project G0502, Elmore County
Hydro
600 MWWithdrawn / abandoned Elmore, IDWest Nov 2014target 2017
Onshore wind project G0499, Elmore County
Onshore wind
250 MWWithdrawn / abandoned Elmore, IDWest Sep 2014target 2017
Solar project 434, Ada County
Solar
80.0 MWWithdrawn / abandoned Ada, IDWest Jul 2014
Solar project 437, Elmore County
Solar
70.0 MWWithdrawn / abandoned Elmore, IDWest Oct 2014
Geothermal project G0497, Cassia County
Geothermal
45.0 MWWithdrawn / abandoned Cassia, IDWest Jan 2014target 2017
Solar project 439, Elmore County
Solar
30.0 MWWithdrawn / abandoned Elmore, IDWest Oct 2014
Solar project 452, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Solar project 457, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Solar project 453, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Solar project 450, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Solar project 449, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Solar project 427, Owyhee County
Solar
20.0 MWWithdrawn / abandoned Owyhee, IDWest Jun 2014
Solar project 456, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Solar project 451, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Solar project 455, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Solar project 438, Elmore County
Solar
20.0 MWWithdrawn / abandoned Elmore, IDWest Oct 2014
Solar project 440, Elmore County
Solar
20.0 MWWithdrawn / abandoned Elmore, IDWest Oct 2014
Solar project 454, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Solar project 436, Power County
Solar
20.0 MWWithdrawn / abandoned Power, IDWest Oct 2014
Solar project 448, Bingham County
Solar
13.0 MWWithdrawn / abandoned Bingham, IDWest Dec 2014
Solar project 447, Bingham County
Solar
13.0 MWWithdrawn / abandoned Bingham, IDWest Dec 2014
Solar project 446, Camas County
Solar
13.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Solar project 442, Elmore County
Solar
10.0 MWWithdrawn / abandoned Elmore, IDWest Nov 2014
Gas project G0503, Bonner County
Gas
10.0 MWWithdrawn / abandoned Bonner, IDWest Nov 2014target 2016
Solar project 445, Elmore County
Solar
10.0 MWWithdrawn / abandoned Elmore, IDWest Dec 2014
Solar project 422, Elmore County
Solar
10.0 MWWithdrawn / abandoned Elmore, IDWest Jan 2014
Solar project 421, Elmore County
Solar
10.0 MWWithdrawn / abandoned Elmore, IDWest Jan 2014
Solar project 444, Elmore County
Solar
7.5 MWWithdrawn / abandoned Elmore, IDWest Nov 2014
Solar project 443, Elmore County
Solar
6.0 MWWithdrawn / abandoned Elmore, IDWest Nov 2014
Hydro project 430, Twin Falls County
Hydro
0.6 MWWithdrawn / abandoned Twin Falls, IDWest Jul 2014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)