πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Idaho (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1312.8 MW
Active in queue455 MW2 requests
Agreement signed455 MW2 requests
Withdrawn113,057 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project 576, Gooding County
Other Β· West Point RNG LLC
3.2 MWOperating Gooding, IDWest Jan 20202024
Hydro project 579, Twin Falls County
Hydro Β· Lateral 10 Venture
2.6 MWOperating Twin Falls, IDWest Apr 2020target 2020
Hydro project 596, Twin Falls County
Hydro Β· Crystal Springs Hydroelectric, L.P.
2.5 MWOperating Twin Falls, IDWest Jun 2020target 2021
Hydro project 584, Twin Falls County
Hydro Β· Russell LeMoyne
0.8 MWOperating Twin Falls, IDWest Jun 2020target 2020
Hydro project 594, Twin Falls County
Hydro Β· J.M. Miller Enterprises, Inc.
0.6 MWOperating Twin Falls, IDWest Jan 2020target 2020
Hydro project 581, Twin Falls County
Hydro Β· Sagebrush Hydro
0.6 MWOperating Twin Falls, IDWest May 2020target 2020
Hydro project 600, Lemhi County
Hydro Β· Lemhi Hydropower Company
0.5 MWOperating Lemhi, IDWest Oct 2020target 2021
Hydro project 582, Twin Falls County
Hydro Β· Jim Knight Hydro
0.5 MWOperating Twin Falls, IDWest May 2020target 2020
Hydro project 583, Blaine County
Hydro Β· White Water Power Company, Inc
0.4 MWOperating Blaine, IDWest May 2020target 2020
Hydro project 593, Twin Falls County
Hydro Β· Shawpatin Ag Cap LLC.
0.3 MWOperating Twin Falls, IDWest Dec 2020target 2020
Hydro project 589, Twin Falls County
Hydro Β· Scott Kaster
0.3 MWOperating Twin Falls, IDWest Sep 2020target 2020
Other project 592, Bannock County
Other Β· City of Pocatello
0.3 MWOperating Bannock, IDWest Dec 2020target 2020
Hydro project 586, Twin Falls County
Hydro Β· White Water Power Company
0.2 MWOperating Twin Falls, IDWest Jul 2020target 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)