United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Idaho (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown561.0 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn10.2 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 517, Twin Falls County
Solar Β· Jackpot Holdings, LLC
20.0 MWOperating Twin Falls, IDWest Jul 20162022
Solar project 513, Twin Falls County
Solar Β· Jackpot Holdings, LLC
20.0 MWOperating Twin Falls, IDWest Mar 20162022
Solar project 514, Twin Falls County
Solar Β· Jackpot Holdings, LLC
20.0 MWOperating Twin Falls, IDWest Mar 20162022
Hydro project 516, Twin Falls County
Hydro Β· HK Hydro
0.5 MWOperating Twin Falls, IDWest Mar 2016target 2017
Hydro project 515, Lincoln County
Hydro Β· Shorock Hydro, LLC
0.5 MWOperating Lincoln, IDWest Apr 2016target 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)