United States β€Ί Grid β€Ί Interconnection queues β€Ί Delaware

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Delaware (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6687 MW
Active in queue20.0 MW1 requests
Agreement signed0.0 MW0 requests
Withdrawn6687 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore wind project AG2-347, Sussex County
Offshore wind Β· US Wind, Inc
449 MWWithdrawn / abandoned Sussex, DEPJM Feb 2025target 2025
Offshore wind project AH1-634, Sussex County
Offshore wind Β· US Wind, Inc
68.0 MWWithdrawn / abandoned Sussex, DEPJM Feb 2025target 2024
Solar project AH1-585, Sussex County
Solar Β· RWE Solar Development, LLC
50.0 MWWithdrawn / abandoned Sussex, DEPJM Jan 2025target 2024
Solar project AH1-584, Sussex County
Solar Β· RWE Solar Development, LLC
50.0 MWWithdrawn / abandoned Sussex, DEPJM Jan 2025target 2024
Battery storage project AH1-586, Sussex County
Battery storage Β· RWE Solar Development, LLC
45.0 MWWithdrawn / abandoned Sussex, DEPJM Jan 2025target 2024
Solar project AH1-027, Kent County
Solar Β· Calpine Mid-Atlantic Development, LLC
25.0 MWWithdrawn / abandoned Kent, DEPJM Feb 2025target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)