United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Colorado (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown162,652 MW
Active in queue260 MW2 requests
Agreement signed0.0 MW0 requests
Withdrawn162,652 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

16 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GI-2019-1, El Paso County
Solar
450 MWWithdrawn / abandoned El Paso, COWest Feb 2019target 2021
Solar + storage project 1118, Moffat County
Solar + storage
350 MWWithdrawn / abandoned Moffat, COWest Mar 2019target 2023
Solar project GI-2019-2, Pueblo County
Solar
350 MWWithdrawn / abandoned Pueblo, COWest Feb 2019target 2021
Solar project GI-2019-9, Adams County
Solar
200 MWWithdrawn / abandoned Adams, COWest Sep 2019target 2022
Solar + storage project GI-2019-10, Weld County
Solar + storage
200 MWWithdrawn / abandoned Weld, COWest Oct 2019target 2022
Solar + storage project GI-2019-11, Morgan County
Solar + storage
170 MWWithdrawn / abandoned Morgan, COWest Dec 2019target 2022
Solar project 19-09232, Larimer County
Solar
150 MWWithdrawn / abandoned Larimer, COWest Sep 2019target 2023
Solar project GI-2019-8, Adams County
Solar
150 MWWithdrawn / abandoned Adams, COWest Jul 2019target 2022
Solar project BHCT G26, Pueblo County
Solar
125 MWWithdrawn / abandoned Pueblo, COWest Nov 2019target 2022
Solar project BHCT G27, Pueblo County
Solar
100 MWWithdrawn / abandoned Pueblo, COWest Dec 2019target 2022
Solar project 19-04261, Larimer County
Solar
100 MWWithdrawn / abandoned Larimer, COWest Apr 2019target 2021
Solar project 19-09231, Larimer County
Solar
80.0 MWWithdrawn / abandoned Larimer, COWest Sep 2019target 2023
Battery storage project GI-2019-3, Pueblo County
Battery storage
75.0 MWWithdrawn / abandoned Pueblo, COWest Mar 2019target 2022
Battery storage project GI-2014-6, Pueblo County
Battery storage
52.0 MWWithdrawn / abandoned Pueblo, COWest Sep 2019target 2023
Battery storage project GI-2019-4, Pueblo County
Battery storage
50.0 MWWithdrawn / abandoned Pueblo, COWest Mar 2019target 2022
Solar + storage project GI-2019-7, Pueblo County
Solar + storage
50.0 MWWithdrawn / abandoned Pueblo, COWest Jul 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)