United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Colorado (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5770 MW
Active in queue221 MW2 requests
Agreement signed221 MW2 requests
Withdrawn5770 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-2013-2, Lincoln County
Onshore wind
200 MWWithdrawn / abandoned Lincoln, COWest Mar 2013target 2016
Onshore wind project GI-2013-6, Logan County
Onshore wind
200 MWWithdrawn / abandoned Logan, COWest Sep 2013target 2016
Onshore wind project GI-2013-1, Pueblo County
Onshore wind
200 MWWithdrawn / abandoned Pueblo, COWest Feb 2013target 2015
Onshore wind project GI-2013-7, Logan County
Onshore wind
140 MWWithdrawn / abandoned Logan, COWest Sep 2013target 2014
Solar project GI-2013-3, Pueblo County
Solar
30.0 MWWithdrawn / abandoned Pueblo, COWest Apr 2013target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)