πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Colorado (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4354 MW
Active in queue1,557 MW11 requests
Agreement signed354 MW4 requests
Withdrawn123,402 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 2RSC-2020-05, Pueblo County
Solar + storage
250 MWAgreement signed Pueblo, COWest Sep 2020target 2022
Battery storage project 1RSC-2020-02, Pueblo County
Battery storage
75.0 MWAgreement signed Pueblo, COWest Jan 2020target 2022
Gas project GI-2020-05, Weld County
Gas
24.0 MWAgreement signed Weld, COWest Mar 2020target 2020
Hydro project GI-2020-18, Mesa County
Hydro
4.5 MWAgreement signed Mesa, COWest Dec 2020target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)