United States β€Ί Grid β€Ί Interconnection queues β€Ί California

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in California (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown153,148 MW
Active in queue2,907 MW10 requests
Agreement signed2,907 MW10 requests
Withdrawn8616.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Kola
Battery storage
418 MWOperating Alameda, CACAISO May 2016target 2020
Marvel
Battery storage
406 MWOperating Riverside, CACAISO May 20162024
Edsan 1
Solar + storage
384 MWOperating Kern, CACAISO May 20162023
Proxima Solar
Solar + storage
352 MWOperating Stanislaus, CACAISO May 20162024
Willy 9
Solar + storage
338 MWOperating Kern, CACAISO May 20162025
Sol Catcher BESS
Solar + storage
335 MWOperating Riverside, CACAISO May 20162024
Daggett Solar 2
Solar + storage
300 MWOperating San Bernardino, CACAISO May 20162023
Sagebrush Solar 2
Battery storage
179 MWOperating Kern, CACAISO May 20162024
Tropico Solar
Solar + storage
152 MWOperating Kern, CACAISO May 20162022
Daggett Solar 1
Battery storage
114 MWOperating San Bernardino, CACAISO May 20162025
Cyclone Solar
Solar + storage
65.0 MWOperating Kern, CACAISO May 20162025
Northern Orchard Solar 2
Solar
50.0 MWOperating Kern, CACAISO May 20162025
Cascade Energy Storage
Battery storage
25.2 MWOperating San Joaquin, CACAISO May 20162023
Vista Energy Storage 2
Battery storage
20.0 MWOperating San Diego, CACAISO May 20162018
Spi Sonora
Other
10.9 MWOperating Tuolumne, CACAISO May 20162018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)