United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Arkansas (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4475 MW
Active in queue475 MW4 requests
Agreement signed375 MW3 requests
Withdrawn211,843 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J586, Mississippi County
Solar
175 MWAgreement signed Mississippi, ARMISO May 20162024
Solar project J603, Ashley County
Solar
100 MWAgreement signed Ashley, ARMISO May 20162024
Solar project J552, Lee County
Solar
100 MWAgreement signed Lee, ARMISO Mar 20162024
Solar project J680, Ashley County
Solar
100 MWUnder construction Ashley, ARMISO Jul 20162024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)