United States β€Ί Grid β€Ί Interconnection queues β€Ί Arizona

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Arizona (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown148,212 MW
Active in queue13.5 GW43 requests
Agreement signed0.0 MW0 requests
Withdrawn148,212 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

14 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q2507, Pinal County
Solar + storage
2,538 MWWithdrawn / abandoned Pinal, AZWest Feb 2025target 2027
Solar + storage project Q2501, Navajo County
Solar + storage
1,027 MWWithdrawn / abandoned Navajo, AZWest Feb 2025target 2029
Solar + storage project Q2502, Pinal County
Solar + storage
911 MWWithdrawn / abandoned Pinal, AZWest Feb 2025target 2027
Solar + storage project Q2506, Navajo County
Solar + storage
786 MWWithdrawn / abandoned Navajo, AZWest Feb 2025target 2029
Solar + storage project Q2514, Navajo County
Solar + storage
600 MWWithdrawn / abandoned Navajo, AZWest Feb 2025target 2028
Battery storage project Q2513, Pinal County
Battery storage
529 MWWithdrawn / abandoned Pinal, AZWest Feb 2025target 2029
Solar + storage project Q2505, Maricopa County
Solar + storage
405 MWWithdrawn / abandoned Maricopa, AZWest Feb 2025target 2028
Solar + storage project Q2504, Maricopa County
Solar + storage
405 MWWithdrawn / abandoned Maricopa, AZWest Feb 2025target 2028
Solar + storage project Q2517, Pinal County
Solar + storage
373 MWWithdrawn / abandoned Pinal, AZWest Feb 2025target 2028
Other project Q613, Maricopa County
Other
232 MWWithdrawn / abandoned Maricopa, AZWest May 2025target 2026
Battery storage project Q2508, Maricopa County
Battery storage
206 MWWithdrawn / abandoned Maricopa, AZWest Feb 2025target 2029
Battery storage project Q2509, Pinal County
Battery storage
105 MWWithdrawn / abandoned Pinal, AZWest Feb 2025target 2028
Other project Q600, Navajo County
Other
75.0 MWWithdrawn / abandoned Navajo, AZWest May 2025target 2029
Other project Q601, Yuma County
Other
21.6 MWWithdrawn / abandoned Yuma, AZWest May 2025target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)