United States β€Ί Grid β€Ί Interconnection queues β€Ί Arizona

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Arizona (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7981 MW
Active in queue250 MW2 requests
Agreement signed0.0 MW0 requests
Withdrawn7981 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Titan Solar
Gas
300 MWWithdrawn / abandoned Maricopa, AZCAISO Apr 2015target 2020
Gas project 43, Pima County
Gas
206 MWWithdrawn / abandoned Pima, AZWest Feb 2015target 2018
Palomas Solar Project
Solar
200 MWWithdrawn / abandoned Yuma, AZCAISO Apr 2015target 2018
Onshore wind project 644, Navajo County
Onshore wind
200 MWWithdrawn / abandoned Navajo, AZWest Feb 2015target 2018
Solar project Q36, Pinal County
Solar
48.0 MWWithdrawn / abandoned Pinal, AZWest Feb 2015target 2019
Solar project Q231, Cochise County
Solar
17.5 MWWithdrawn / abandoned Cochise, AZWest Oct 2015target 2016
Solar project Q37, Pinal County
Solar
9.0 MWWithdrawn / abandoned Pinal, AZWest Apr 2015target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)