Completed queue projects in Arizona (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5590 MW
Active in queue254 MW3 requests
Agreement signed20.0 MW1 requests
Withdrawn305,612 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q23, Maricopa County
Solar + storage
183 MWOperating Maricopa, AZWest Jun 20162023
Solar project Q21, Maricopa County
Solar
150 MWOperating Maricopa, AZWest Jan 20162021
Solar project Q22, Maricopa County
Solar
125 MWOperating Maricopa, AZWest Feb 2016target 2025
Solar + storage project Q236/272, Yuma County
Solar + storage
70.0 MWOperating Yuma, AZWest Mar 2016target 2021
Mesquite Solar 4
Solar + storage
62.5 MWOperating Maricopa, AZCAISO May 20162024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)