United States β€Ί Grid β€Ί Interconnection queues β€Ί Arizona

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Arizona (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4271 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn364,766 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project Q196, Coconino County
Other
161 MWOperating Coconino, AZWest May 2011target 2021
Solar project Q24, Pinal County
Solar
45.0 MWOperating Pinal, AZWest Jul 20112015
Solar project Q205, Yuma County
Solar
35.0 MWOperating Yuma, AZWest Sep 2011target 2012
Solar project Q202, Navajo County
Solar
30.0 MWOperating Navajo, AZWest Jul 2011target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)