Completed queue projects in Arizona (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5905 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn1005,781 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q15, Maricopa County
Solar + storage
600 MWOperating Maricopa, AZWest Jul 20102019
Mesquite Solar 1 (Fka Mesquite Generation)
Solar
165 MWOperating Maricopa, AZCAISO Jul 20102014
Onshore wind project Q113, Coconino County
Onshore wind
101 MWOperating Coconino, AZWest Mar 2010target 2011
Solar project Q20, Pinal County
Solar
20.0 MWOperating Pinal, AZWest Nov 20102012
Solar project Q162, Yavapai County
Solar
19.0 MWOperating Yavapai, AZWest Aug 2010target 2012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)