United States β€Ί Grid β€Ί Interconnection queues β€Ί Alabama

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Alabama (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown112,004 MW
Active in queue1,007 MW8 requests
Agreement signed460 MW3 requests
Withdrawn112,004 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project IC-1253, Baldwin County
Gas
684 MWWithdrawn / abandoned Baldwin, ALSoutheast Mar 2024
Battery storage project 670, Jackson County
Battery storage
200 MWWithdrawn / abandoned Jackson, ALSoutheast Oct 2024
Solar project IC-1273, Clarke County
Solar
180 MWWithdrawn / abandoned Clarke, ALSoutheast Mar 2024
Solar project IC-1277, Escambia County
Solar
150 MWWithdrawn / abandoned Escambia, ALSoutheast Apr 2024
Solar project 667, Lawrence County
Solar
150 MWWithdrawn / abandoned Lawrence, ALSoutheast Oct 2024
Solar project IC-1278, Escambia County
Solar
150 MWWithdrawn / abandoned Escambia, ALSoutheast Apr 2024
Solar project 635, Jackson County
Solar
120 MWWithdrawn / abandoned Jackson, ALSoutheast Jul 2024
Solar + storage project 639, Jackson County
Solar + storage
100 MWWithdrawn / abandoned Jackson, ALSoutheast Aug 2024
Solar project 617, Caldwell County
Solar
100 MWWithdrawn / abandoned Caldwell, ALSoutheast Jun 2024
Solar project IC-1242, Dallas County
Solar
100 MWWithdrawn / abandoned Dallas, ALSoutheast Mar 2024
Solar project IC-1239, Chambers County
Solar
70.0 MWWithdrawn / abandoned Chambers, ALSoutheast Jan 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)