United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Southeast (non-ISO utilities) (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4125 MW
Active in queue27.0 MW2 requests
Agreement signed27.0 MW2 requests
Withdrawn3214.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project 33, Georgetown County
Other Β· IPCO
65.0 MWOperating Georgetown, SCSoutheast Oct 2011target 2012
Other project 32, Allendale County
Other Β· SRE
19.9 MWOperating Allendale, SCSoutheast Feb 2011target 2012
Other project 31, Dorchester County
Other Β· SRE
19.9 MWOperating Dorchester, SCSoutheast Feb 2011target 2012
Other project 30, Kershaw County
Other
19.9 MWOperating Kershaw, SCSoutheast Feb 2011target 2012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)