United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in MISO (Midcontinent) (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown121,465 MW
Active in queue70.0 MW1 requests
Agreement signed70.0 MW1 requests
Withdrawn5110.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J233, Marshall County
Gas
700 MWOperating Marshall, IAMISO Nov 20112018
Onshore wind project J235, Huron County
Onshore wind
110 MWOperating Huron, MIMISO Nov 20112016
Onshore wind project J202, Tuscola County
Onshore wind
101 MWOperating Tuscola, MIMISO Feb 20112014
Gas project J200, Morton County
Gas
99.0 MWOperating Morton, NDMISO Feb 20112016
Battery storage project J229, Mason County
Battery storage
70.0 MWOperating Mason, MIMISO Sep 20112015
Battery storage project J228, Mason County
Battery storage
70.0 MWOperating Mason, MIMISO Sep 20112014
Battery storage project J231, Mason County
Battery storage
70.0 MWOperating Mason, MIMISO Sep 20112017
Battery storage project J227, Mason County
Battery storage
70.0 MWOperating Mason, MIMISO Sep 20112015
Battery storage project J226, Mason County
Battery storage
70.0 MWOperating Mason, MIMISO Sep 20112013
Onshore wind project J196, Vermilion County
Onshore wind
50.0 MWOperating Vermilion, ILMISO Feb 20112013
Coal project J232, Randolph County
Coal
35.0 MWOperating Randolph, ILMISO Nov 20112018
Onshore wind project J201, Bay County
Onshore wind
20.0 MWOperating Bay, MIMISO Feb 20112013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)