πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Queue projects under construction in MISO (Midcontinent) (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3598 MW
Active in queue82.2 GW435 requests
Agreement signed881 MW6 requests
Withdrawn56794.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1730, Dunn County
Solar
300 MWUnder construction Dunn, WIMISO Mar 2022target 2027
Solar project J1750, Marquette County
Solar
150 MWUnder construction Marquette, MIMISO Apr 2022target 2026
Solar project J1752, Portage County
Solar
148 MWUnder construction Portage, WIMISO May 2022target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)