πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Mississippi, MISO (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3300 MW
Active in queue300 MW3 requests
Agreement signed250 MW2 requests
Withdrawn5650 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1672, Hinds County
Solar
150 MWAgreement signed Hinds, MSMISO Jun 2020target 2025
Solar project J1748, Desoto County
Solar
100 MWAgreement signed Desoto, MSMISO Jul 2020target 2025
Solar project J1747, Madison County
Solar
50.0 MWUnder construction Madison, MSMISO Jun 2020target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)