United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Iowa, MISO (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2350 MW
Active in queue350 MW2 requests
Agreement signed0.0 MW0 requests
Withdrawn9986 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J877, Palo Alto County
Solar
250 MWUnder construction Palo Alto, IAMISO Jun 2017target 2023
Onshore wind project J898, Howard County
Onshore wind
100 MWUnder construction Howard, IAMISO Jun 2017target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)