Interconnection queue in CAISO (California) (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9894 MW
Active in queue894 MW9 requests
Agreement signed894 MW9 requests
Withdrawn7010.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
White Wing Ranch Solar
Solar + storage
400 MWAgreement signed Yuma, AZCAISO Apr 2014target 2026
Gaskell West
Solar + storage
187 MWAgreement signed Kern, CACAISO Apr 2014target 2026
Willow Springs Solar 3
Battery storage
50.0 MWAgreement signed Kern, CACAISO Apr 2014target 2026
North Johnson Energy Center
Battery storage
50.0 MWAgreement signed San Diego, CACAISO Apr 2014target 2026
Chula Vista Energy Center 2
Battery storage
50.0 MWAgreement signed San Diego, CACAISO Apr 2014target 2026
Ares Nevada
Battery storage
44.0 MWAgreement signed Nye, NVCAISO Apr 2014target 2027
Little Bear Solar 1
Solar + storage
40.0 MWAgreement signed Fresno, CACAISO Apr 20142020
Little Bear Solar 2
Solar + storage
40.0 MWAgreement signed Fresno, CACAISO Apr 20142020
Escondido Energy Center 2
Battery storage
33.0 MWAgreement signed San Diego, CACAISO Apr 2014target 2030

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)