Queue requests in study in CAISO (California) (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown32,352 MW
Active in queue21.8 GW36 requests
Agreement signed19.4 GW33 requests
Withdrawn9539.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Arida 2 Solar Farm
Solar + storage
1,400 MWIn study Clark, NVCAISO Apr 2019target 2029
Hoodini
Solar + storage
910 MWIn study Yuma, AZCAISO Apr 2019target 2028
Air Station 1
Solar + storage
42.1 MWIn study Kings, CACAISO Apr 2019target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)