United States › Grid › Interconnection queues › Idaho

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Idaho — page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown55888.2 GW
Active in queue21.0 GW83 requests
Agreement signed4,070 MW23 requests
Withdrawn55888.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

558 requests · page 8 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 467, Elmore County
Solar
20.0 MWWithdrawn / abandoned Elmore, IDWest Feb 2015
Onshore wind project 135, Twin Falls County
Onshore wind
20.0 MWWithdrawn / abandoned Twin Falls, IDWest Jun 2005target 2005
Solar project 358, Owyhee County
Solar
20.0 MWWithdrawn / abandoned Owyhee, IDWest Oct 2010
Solar project 456, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Onshore wind project G0395, Cassia County
Onshore wind
20.0 MWWithdrawn / abandoned Cassia, IDWest Nov 2009target 2010
Onshore wind project 258, Elmore County
Onshore wind
20.0 MWWithdrawn / abandoned Elmore, IDWest Jun 2008target 2010
Battery storage project 748, Jerome County
Battery storage
20.0 MWWithdrawn / abandoned Jerome, IDWest Jun 2024
Battery storage project 756, Elmore County
Battery storage
20.0 MWWithdrawn / abandoned Elmore, IDWest Jan 2025
Onshore wind project 298, Owyhee County
Onshore wind
20.0 MWWithdrawn / abandoned Owyhee, IDWest Sep 2009
Onshore wind project 325, Twin Falls County
Onshore wind
20.0 MWWithdrawn / abandoned Twin Falls, IDWest Mar 2010
Solar project 451, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Solar project 482, Ada County
Solar
20.0 MWWithdrawn / abandoned Ada, IDWest Apr 2015
Solar project 356, Owyhee County
Solar
20.0 MWWithdrawn / abandoned Owyhee, IDWest Sep 2010
Solar project 345, Owyhee County
Solar
20.0 MWWithdrawn / abandoned Owyhee, IDWest Jul 2010
Solar project 455, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Onshore wind project 352, Blaine County
Onshore wind
20.0 MWWithdrawn / abandoned Blaine, IDWest Aug 2010
Onshore wind project 155, Bonneville County
Onshore wind · PacifiCorp Commercial & Trading
20.0 MWWithdrawn / abandoned Bonneville, IDWest Aug 2007target 2009
Battery storage project 749, Jerome County
Battery storage
20.0 MWWithdrawn / abandoned Jerome, IDWest Jun 2024
Solar project 463, Bingham County
Solar
20.0 MWWithdrawn / abandoned Bingham, IDWest Jan 2015
Other project 331, Elmore County
Other
20.0 MWWithdrawn / abandoned Elmore, IDWest May 2010
Solar project 663, Caribou County
Solar
20.0 MWWithdrawn / abandoned Caribou, IDWest Apr 2015target 2016
Solar project 342, Elmore County
Solar
20.0 MWWithdrawn / abandoned Elmore, IDWest Jul 2010
Onshore wind project 350, Twin Falls County
Onshore wind
20.0 MWWithdrawn / abandoned Twin Falls, IDWest Aug 2010
Solar project 438, Elmore County
Solar
20.0 MWWithdrawn / abandoned Elmore, IDWest Oct 2014
Solar project 488, Elmore County
Solar
20.0 MWWithdrawn / abandoned Elmore, IDWest Apr 2015
Onshore wind project 323, Twin Falls County
Onshore wind
20.0 MWWithdrawn / abandoned Twin Falls, IDWest Mar 2010
Solar project 667, Jefferson County
Solar
20.0 MWWithdrawn / abandoned Jefferson, IDWest May 2015target 2016
Solar project 440, Elmore County
Solar
20.0 MWWithdrawn / abandoned Elmore, IDWest Oct 2014
Onshore wind project G0445, Cassia County
Onshore wind
20.0 MWWithdrawn / abandoned Cassia, IDWest Dec 2010target 2011
Onshore wind project G0246, Cassia County
Onshore wind
20.0 MWWithdrawn / abandoned Cassia, IDWest Nov 2006target 2007
Other project 295, Gem County
Other
20.0 MWWithdrawn / abandoned Gem, IDWest May 2009
Onshore wind project 399, Owyhee County
Onshore wind
20.0 MWWithdrawn / abandoned Owyhee, IDWest Jul 2012
Onshore wind project G0412, Cassia County
Onshore wind
20.0 MWWithdrawn / abandoned Cassia, IDWest Mar 2010target 2011
Solar project 312, Elmore County
Solar
20.0 MWWithdrawn / abandoned Elmore, IDWest Nov 2009
Solar project 454, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Solar project 464, Bingham County
Solar
20.0 MWWithdrawn / abandoned Bingham, IDWest Jan 2015
Solar project 487, Elmore County
Solar
20.0 MWWithdrawn / abandoned Elmore, IDWest Apr 2015
Onshore wind project 322, Twin Falls County
Onshore wind
20.0 MWWithdrawn / abandoned Twin Falls, IDWest Mar 2010
Onshore wind project 324, Twin Falls County
Onshore wind
20.0 MWWithdrawn / abandoned Twin Falls, IDWest Mar 2010
Onshore wind project G0388, Cassia County
Onshore wind
20.0 MWWithdrawn / abandoned Cassia, IDWest Nov 2009target 2010
Solar project 485, Minidoka County
Solar
20.0 MWWithdrawn / abandoned Minidoka, IDWest Apr 2015
Onshore wind project 347, Owyhee County
Onshore wind
20.0 MWWithdrawn / abandoned Owyhee, IDWest Aug 2010
Onshore wind project G0442, Cassia County
Onshore wind
20.0 MWWithdrawn / abandoned Cassia, IDWest Oct 2010target 2011
Onshore wind project G0248, Cassia County
Onshore wind
20.0 MWWithdrawn / abandoned Cassia, IDWest Nov 2006target 2007
Solar project 436, Power County
Solar
20.0 MWWithdrawn / abandoned Power, IDWest Oct 2014
Solar project 465, Bingham County
Solar
20.0 MWWithdrawn / abandoned Bingham, IDWest Jan 2015
Onshore wind project 184, Elmore County
Onshore wind
19.8 MWWithdrawn / abandoned Elmore, IDWest Oct 2006target 2007
Onshore wind project 188, Elmore County
Onshore wind
19.8 MWWithdrawn / abandoned Elmore, IDWest Oct 2006target 2007
Onshore wind project 154, Bonneville County
Onshore wind
19.8 MWWithdrawn / abandoned Bonneville, IDWest Aug 2007target 2009
Onshore wind project 189, Elmore County
Onshore wind
19.8 MWWithdrawn / abandoned Elmore, IDWest Oct 2006target 2007
Page 8 of 12

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)