🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Mexico

OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in New Mexico — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown538,278 MW
Active in queue34.0 GW164 requests
Agreement signed8,278 MW53 requests
Withdrawn40758.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

53 requests · page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project SGI-PNM-2017-08, Luna County
Solar
11.0 MWAgreement signed Luna, NMWest Jun 2017target 2019
Solar project IA-PNM-2017-01, Cibola County
Solar · NextEra Energy
10.0 MWAgreement signed Cibola, NMWest Jan 2017target 2021
Solar project SGI-PNM-2017-09, Luna County
Solar
8.3 MWAgreement signed Luna, NMWest Jun 2017target 2019
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)