United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Southeast (non-ISO utilities) (2020 requests) β€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown557,020 MW
Active in queue7,020 MW55 requests
Agreement signed4,069 MW24 requests
Withdrawn17830.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

55 requests Β· page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 126062, Alamance County
Solar
35.0 MWAgreement signed Alamance, NCSoutheast Mar 2020target 2026
Solar project 126066, Greenwood County
Solar
34.0 MWAgreement signed Greenwood, SCSoutheast Mar 2020target 2026
Gas project IC-1012, Autauga County
Gas
27.0 MWIn study Autauga, ALSoutheast Oct 2020
Battery storage project 461, Loudon County
Battery storage
22.0 MWAgreement signed Loudon, TNSoutheast Nov 2020target 2024
Solar + storage project IC-903, Liberty County
Solar + storage
13.0 MWAgreement signed Liberty, GASoutheast Aug 2020target 2023
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)