Octary Global · France · Hydro
DTPS S01-STOCKAGE N0 01 DE DTPS
Saint-Avold · Grand Est · Operating
17.50
MW installed as reported
2024-07-26
Commissioning date, if provided

Engineering and capacity
- Technology
- Hydro
- Detailed technology
- Batterie
- Fuel
- Not supplied
- Installed power
- 17.500 MW
- Storage energy
- 17500.000
- Voltage
- 63 kV
Location and responsible parties
- Commune
- Saint-Avold
- Department
- Moselle
- Region
- Grand Est
- Location accuracy
- Commune only; exact site not verified
- Owner
- Not verified
- Operator
- Not verified
- Network manager
- RTE
Project timeline
- Commissioned
- 2024-07-26
- Connected
- 2024-07-26
- Disconnected
- Not reported
- Reported status
- Operating
Connection and disconnection dates do not independently establish complete station construction or decommissioning history.
Technology graphics
Technology illustrations are reusable from Octary's UK atlas and are schematic, not photographs of this particular plant.

Source record
- EIC identifier
- 17W0000021449653
- Source family
- fr-rte-register