Octary Global · France · Hydro
BLENOS01-STOCKAGE N0 01 DE BLENOD
Blénod-lès-Pont-à-Mousson · Grand Est · Operating
15.00
MW installed as reported
2024-07-01
Commissioning date, if provided

Engineering and capacity
- Technology
- Hydro
- Detailed technology
- Batterie
- Fuel
- Not supplied
- Installed power
- 15.000 MW
- Storage energy
- 15000.000
- Voltage
- 400 kV
Location and responsible parties
- Commune
- Blénod-lès-Pont-à-Mousson
- Department
- Meurthe-et-Moselle
- Region
- Grand Est
- Location accuracy
- Commune only; exact site not verified
- Owner
- Not verified
- Operator
- Not verified
- Network manager
- RTE
Project timeline
- Commissioned
- 2024-07-01
- Connected
- 2024-07-01
- Disconnected
- Not reported
- Reported status
- Operating
Connection and disconnection dates do not independently establish complete station construction or decommissioning history.
Technology graphics
Technology illustrations are reusable from Octary's UK atlas and are schematic, not photographs of this particular plant.

Source record
- EIC identifier
- 17W0000021448673
- Source family
- fr-rte-register