Boundary Lane
Boundary Lane is a 6.15 MW onshore wind farm in North East England, operated by EDF Energy. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- North East
- England
Key facts
- Installed capacity
- 6.15 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- EDF Energy
- Region
- North East
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- DH8 9LQ
- Coordinates
- 54.8478, -1.9282
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Boundary Lane compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 6.15 MW station would generate roughly 14 GWh of electricity in a year, similar to the annual use of about 5,190 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in North East All run by EDF EnergyNearby generating sites
- Kiln Pit Hill Β· 14 MW onshore wind farm4.3 km
- Tow Law Β· 2.31 MW onshore wind farm11.5 km
- Greencroft Β· 4.93 MW solar farm12.6 km
- High Hedley I Β· 2.4 MW onshore wind farm14.4 km
- High Hedley II Β· 5.2 MW onshore wind farm14.4 km
- Holmside RO Β· 2.75 MW onshore wind farm14.9 km
- Broomhill Β· 8 MW onshore wind farm15.3 km
- Holmside Β· 2.3 MW onshore wind farm16.0 km
Also operated by EDF Energy
EDF Energy operates 48 sites in the register. Largest first:
- Hinkley Point C Β· nuclear power station3,260 MW
- West Burton A Power Station Β· coal-fired power station2,012 MW
- Cottam Power Station Β· coal-fired power station2,008 MW
- Heysham 2 Β· nuclear power station1,240 MW
- Torness Β· nuclear power station1,200 MW
- Sizewell B Β· nuclear power station1,198 MW
- Hartlepool Β· nuclear power station1,185 MW
- Heysham 1 Β· nuclear power station1,060 MW
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Developer / operator
- EDF
- Planning authority
- County Durham
- Planning reference
- 09/00092/CCMEIA
- Application submitted
- 16 June 2009
- Permission granted
- 17 February 2011
- Construction started
- 1 September 2012
- Began operating
- 31 March 2013
- Capacity in planning record
- 6 MW
- Address
- Shotley Quarter, Whittonstall, Nr Consett, Co Durham. DH8 9, County Durham
- REPD reference
- 3674
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.