Battery Storage

Wormald Green Solar Farm

Land Comprising Field At 431305 464500 Station Lane Burton Leonard, North Yorkshire, HG3

Wormald Green Solar Farm is a battery storage project in Yorkshire and Humber. The applicant or operator on record is Harmony Energy Limited. Planning permission has been granted as of July 2025 and it is awaiting construction. The determining authority is North Yorkshire, refere…

Consented / Approved
Project stageConsented
  1. PlanningDec 2023 (completed)
  2. ConsentedJul 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2026-03-31.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

πŸ“‹ Project Overview

Wormald Green Solar Farm is a battery storage project in Yorkshire and Humber. The applicant or operator on record is Harmony Energy Limited. Planning permission has been granted as of July 2025 and it is awaiting construction. The determining authority is North Yorkshire, reference ZC23/04361/EIAMAJ.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperHarmony Energy Limited
Owner / operatorHarmony Energy Limited
Year consented2025
LocationLand Comprising Field At 431305 464500 Station Lane Burton Leonard, North Yorkshire, HG3
RegionYorkshire and Humber
Coordinates54.0690635Β°N, 1.5028271Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID8540

πŸ“… Project Timeline

2023-12-04
2025-07-31