Wooler St. Mary / CLNR ESS2-2

Wooler, Northumberland, Northumberland, NE71 6NF

Wooler St. Mary / CLNR ESS2-2 is a 0.1 MW battery storage project in North East. The applicant or operator on record is Northern Powergrid. The scheme is currently in the planning system. The determining authority is Northumberland.…

Decommissioned Β· Target 2013
Project stageClosed
  1. Planning (completed)
  2. Consented (completed)
  3. ConstructionAug 2013 (completed)
  4. OperatingSep 2013 (completed)
  5. Closed (current stage)

Status in the official register: Decommissioned.

Official register: July 2026

Recorded status: Decommissioned. Source record updated 2016-10-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

0.100 MW
Power Capacity
2013
Target Date

πŸ“‹ Project Overview

Wooler St. Mary / CLNR ESS2-2 is a 0.1 MW battery storage project in North East. The applicant or operator on record is Northern Powergrid. The scheme is currently in the planning system. The determining authority is Northumberland.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)0.100 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperNorthern Powergrid
Owner / operatorNorthern Powergrid
Construction started2013
Commissioned / target2013
LocationWooler, Northumberland, Northumberland, NE71 6NF
RegionNorth East
Coordinates55.5455191Β°N, 2.0128731Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2013-08-15
2013-09-15