Woodsend Road, Urmston - Battery Energy Storage is a 0.2 MW battery storage project in North West. The applicant or operator on record is AMP Clean Energy. The scheme is currently in the planning system, submitted May 2026. The determining authority is Trafford, reference 119024/β¦
In Planning
Project stageIn planning
PlanningMay 2026 (current stage)
Consented (not yet reached)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Application Submitted.
Official register: July 2026
Recorded status: Planning Application Submitted. Source record updated date not supplied.
Registered planning capacity; not measured generation.
Woodsend Road, Urmston - Battery Energy Storage is a 0.2 MW battery storage project in North West. The applicant or operator on record is AMP Clean Energy. The scheme is currently in the planning system, submitted May 2026. The determining authority is Trafford, reference 119024/FUL/26.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.