Battery Storage

Woodlands Farm, Clapton - Ground Mounted Solar Park

Woodlands Farm Woodlands Lane Clapton Berkeley, Gloucestershire, GL13 9QU

Woodlands Farm, Clapton - Ground Mounted Solar Park is a battery storage project in South West. The applicant or operator on record is Ecotricity Generation Limited. Planning permission has been granted as of August 2025 and it is awaiting construction. The determining authority …

Consented / Approved
Project stageConsented
  1. PlanningOct 2022 (completed)
  2. ConsentedAug 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2026-06-17.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

πŸ“‹ Project Overview

Woodlands Farm, Clapton - Ground Mounted Solar Park is a battery storage project in South West. The applicant or operator on record is Ecotricity Generation Limited. Planning permission has been granted as of August 2025 and it is awaiting construction. The determining authority is Stroud, reference S.22/1955/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperEcotricity Generation Limited
Owner / operatorEcotricity Generation Limited
Year consented2025
LocationWoodlands Farm Woodlands Lane Clapton Berkeley, Gloucestershire, GL13 9QU
RegionSouth West
Coordinates51.680205Β°N, 2.4885516Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID11267
Mounting Type for SolarGround

πŸ“… Project Timeline

2022-10-24
2025-08-05