North East Of Woodlands Farm Calcott Hill Sturry, Kent, CT3 4NA
Woodlands Farm, Calcott Hill - Battery Energy Storage is a 227.5 MW battery storage project in South East. The applicant or operator on record is Sky UK Development Limited. Planning permission has been granted as of May 2026 and it is awaiting construction. The determining authoβ¦
Consented / Approved
Project stageConsented
PlanningMar 2025 (completed)
ConsentedMay 2026 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2026-06-17.
Registered planning capacity; not measured generation.
Woodlands Farm, Calcott Hill - Battery Energy Storage is a 227.5 MW battery storage project in South East. The applicant or operator on record is Sky UK Development Limited. Planning permission has been granted as of May 2026 and it is awaiting construction. The determining authority is Canterbury, reference CA/25/00418.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
227.500 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Sky UK Development Limited
Owner / operator
Sky UK Development Limited
Year consented
2026
Location
North East Of Woodlands Farm Calcott Hill Sturry, Kent, CT3 4NA