Solar Farm

Woodington Solar Farm (Central)

Woodington Solar Farm, Woodington Road, Woodington Farm, East Wellow, Romsey, Hampshire, SO51 6DQ

Woodington Solar Farm (Central) is a solar farm project in South East. The applicant or operator on record is Woodington Solar Limited. It is recorded as under construction since September 2022. The determining authority is Test Valley, reference 20/00814/FULLS.…

Under Construction
Project stageUnder construction
  1. PlanningApr 2020 (completed)
  2. ConsentedMay 2021 (completed)
  3. ConstructionSep 2022 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2020-04-07.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

πŸ“‹ Project Overview

Woodington Solar Farm (Central) is a solar farm project in South East. The applicant or operator on record is Woodington Solar Limited. It is recorded as under construction since September 2022. The determining authority is Test Valley, reference 20/00814/FULLS.

Site Schematic

SUBSTATION ? ha Β· MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperWoodington Solar Limited
Owner / operatorWoodington Solar Limited
Year consented2021
Construction started2022
LocationWoodington Solar Farm, Woodington Road, Woodington Farm, East Wellow, Romsey, Hampshire, SO51 6DQ
RegionSouth East
Coordinates50.9876185Β°N, 1.567239Β°W

Additional published register fields

Registered technologySolar Photovoltaics
CfD Allocation RoundAR5
CfD Capacity (MW)24
Mounting Type for SolarGround
Solar Site Area (sqm)67800

πŸ“… Project Timeline

2020-04-14
2021-05-24
2022-09-01